1.
PURPOSE
The
purpose of this document is to identify generic requirements applicable to the
testing & commissioning of new Subtransmission Overhead Power Line systems
associated with Essential Energy’s network infrastructure.
This
procedure applies to all new overhead line installations that are to be
connected to Essential Energy’s network. The use of this procedure is for
Accredited Service Providers, Essential Energy staff and accredited
sub-contractors.
The
purpose of undertaking overhead line testing is to prove system integrity after
installation work is completed and before connection to the Essential Energy
Network.
The
tests specified within this procedure are minimum requirements. Additional
tests or amendments to testing requirements may vary depending upon
project/site conditions.
Testing
requirements will be negotiated between Essential Energy & the Accredited
Service provider after submission, to EE by the ASP, a project specific
commissioning program.
2.
KEY
TERMS & DEFINITIONS
AR means authorised
representative. The AR may represent an ASP or EE approved contractor.
ASP means an
accredited service provider, being a person or body accredited under part 10 of
the Electricity Supply (General) regulation 2001, (NSW).
Accreditation
of service providers is administered by the department of Industry &
Investment.
A
list of ASP’s is available on the Industry & Investment website.
ASP3 means a level 3
service provider accredited to carry out design works.
ASP1 means a level 1
service provider accredited to carry out construction works. An ASP1 must have
specific accreditation to carry out underground cable installations.
DIP means design
information package.
EE means Essential
Energy.
HIRAC
Hazard Identification, Risk Assessment and Control.
T&C Plan
means Testing & Commissioning Plan
QCC means EE appointed
Quality Control Coordinator.
3.
TESTING
& COMMISSIONING
All
electricity works shall be designed to be safe for the electrical conditions
likely to be experienced during service and the physical environment in which
they will operate. EE needs to ensure that appropriate tests have been
completed before an installation is commissioned into service for compliance
with the design & specifications. This will require close cooperation
between the ASP1’s construction AR and EE.
EE
will appoint a commissioning manager or QCC auditor as EE’s representative for
coordination purposes.
3.1. Tests
Before
any tests are performed, EE and the AR must agree on the procedures to be used
for the tests and any modification to or deletion from this procedure.
EE’s
QCC auditor shall be notified a minimum of 10 working days prior to the
commencement of line installation or any tests to be undertaken.
The
AR will be responsible for ensuring that the completed work is QA checked and
tested and all records and reports are forwarded to the QCC promptly.
EE’s
QCC auditor may be present to witness the testing procedures, and only with EE
approval shall proceed to test.
Tests
must be carried out in the presence of representatives nominated by the AR and
EE. The AR must provide the results of tests to EE as requested by EE, within a
maximum time period of 10 working days.
All
test results shall be documented and submitted to EE including the following
detail:
- Testing organisation details.
- Date, time and location of test.
- Description of line tested.
- Description of test equipment used including calibration dates.
- Test procedure.
- Test results.
If
tests indicate that corrective works are required to ensure line integrity the
AR must then:
- Undertake, at their cost, all rehabilitation, modification or remediation work required to the reasonable satisfaction of EE.
- Report back to EE in writing when all corrective work has been completed and renegotiate a suitable program to recommence tests.
3.2.Test Equipment.
All
test equipment and instrumentation used for testing shall have been calibrated
by a NATA
Accredited
organisation and have a current test sticker affixed. The AR is responsible for
ensuring that test equipment and instrumentation is traceable.
4. COMMISSIONING
4.1. Testing & Commissioning Plan
(T&C Plan)
Prior
to energising or commissioning any subtransmission overhead line installation a
detailed commissioning plan shall be prepared by the ASP1 and submitted to EE
for approval.
The
T&C Plan shall demonstrate to EE the planning by the ASP1 for the
pre-commissioning activities and shall consolidate and reference the QA process
installation checks and tests, as well as the tests required before and after
completion.
The
commissioning plan must include:
- Single line diagram of final installed network.
- Detailed step by step procedure of the activities (checks & tests) with the sequence clearly documented.
- A proposed schedule.
- Supervisor and employees involved including their accreditation & contact details.
- A summary of pre commissioning checks & tests completed and results.
- Written confirmation that all works undertaken by the ASP for the installation meets the required Australian standards, NSW S & I Rules, EE standards and manufacturer’s requirements for testing of product, plant, equipment and drawings/specification.
- HIRAC & associated SWMS documentation.
4.2. Authority for Placing Major
Electrical/Plant Equipment into Service (CEPG2047)
CEPG2047
applies to all new Major Electrical Plant/Equipment.
The
purpose of procedure CEPG2047 is to ensure that EE’s Network Operations
department receives written notification that all construction and
pre-commissioning checks on major plant/equipment are complete and ready for
service.
Prior
to final commissioning and energising of the high voltage equipment, direct
lines of communication must be established between the ASP’s nominated person,
for site commissioning and ongoing operations, and the designated EE Systems
Operations Centre.
The
CEPG2047 written notification shall be completed by the ASP and submitted to
EE’s QCC auditor for co-ordination with EE’s system operations.
4.3. “As Installed” Detail
On
completion of construction and prior to final commissioning of the overhead
line installation the
ASP
is to provide the following “As Installed” detail to EE :
- Route plan including line schedule & profile.
- Structure earthing schedule including measured values.
- Details of other services crossings.
- Test reports and/or test certificates.
- Inspection reports.
·
Any modified or additional drawings, information
or instructions necessary for the satisfactory completion of the work.
“As
Installed” detail shall be provided to EE in electronic form as well as hard
copy. Electronic documentation is required in the following formats :
- All documentation - Adobe Acrobat “pdf”
- Drawings – Microstation “dgn” or compatible
4.4. Worksite Hazard Identification, Risk
Assessment and Control (HIRAC)
Tests
on overhead lines are potentially hazardous to both personnel undertaking the
test and the general public in the vicinity.
A
Worksite safety management plan shall be prepared for the project and
activities, and will be implemented with an accompanying HIRAC.
The
HIRAC will be carried out, by the ASP1’s authorised person, to determine the
precautions that need to be adopted.
The
HIRAC procedure & associated SWMS are to be submitted to EE’s QCC auditor
for review prior to implementation.
5. PRE MCOMISSIONING
5.1. QA Checks
During
the installation a system of records shall be maintained which provides
objective evidence that requirements have been met, including construction in
accordance with applicable standards, construction drawings/plans and
specifications.
All
records shall be available for audit and review by EE during the installation.
The records should provide full traceability of all quality characteristics and
activities.
During
construction activities QA mechanisms such as check sheets, checklists,
inspection & test plans (ITPs) shall be utilised for an EE representative
to witness and sign off.
EE’s
QCC auditor may be present to witness the installation at hold points, as
required by EE, and work shall not proceed past a hold point without EE
consent.
5.2. Notice of Completion
On
completion of construction works and prior to final commissioning the AR is to
submit a notice of completion to EE’s QCC auditor.
The
completion notice is to include –
·
T&C Plan.
·
CEPG 2047 written notification.
·
“As Installed” Plans and documentation.
A
final inspection/audit will be carried out by EE’s QCC auditor along with the
ASP1’s AR.
5.3. Final Inspection/Audit
The
purpose of the final inspection/audit is to ensure the new asset is acceptable
to EE for connection to EE’s transmission network.
A
review will be undertaken of the following –
Vegetation
& Environmental Management.
Access.
Construction
Quality Assurance including visual inspection of works and sign off of non-conformance
issues.
6. PRE
COMISSIONING TESTS
The
purpose of pre commissioning tests are to confirm line integrity &
compliance with the earthing,
EPR
& protection studies carried out and approved for the project.
The
required pre commissioning tests for subtransmission overhead lines are :
- Structure Earth Resistance Test.
- Phase Continuity Test
- Insulation Resistance Test.
- Earth Current Injection Test.
- OPGW Tests.
6.1. Structure Earth Resistance Test
After
completion of structure installation but prior to the installation of any
OHEW/OPGW, the electrical resistance of structure earthing shall be measured by
the ASP1. EE’s QCC auditor or nominated representative may be present to
witness tests. The results shall be supplied to EE’s QCC auditor without delay
for review.
The
ASP1 may be directed by EE to install supplementary earthing where readings
exceed the required value. The installation of supplementary earthing shall be
in accordance with EE standards and shall be completed prior to the
installation of OHEW/OPGW. The supplementary earthing shall be installed so as
to comply with the specified electrical resistance of each structure to earth.
6.2. Phase Continuity Test
A
phasing check shall be completed prior to commissioning to ensure that the
phases are correctly aligned to synchronise with the network to which the line
is to be connected.
6.3. Insulation Resistance Test
An
insulation resistance check ie megger test, shall be completed prior to
commissioning to ensure no inadvertent short circuits.
6.4. Earth Current Injection Test
For
shielded lines, earth current injection tests shall be undertaken and the
following measurements taken at each support structure –
- Line – Earth Impedance.
- Step & Touch Potential.
- Earth Potential rise.
- Zero Sequence Impedance.
Recorded
test measurements are to confirm compliance with the requirements of AS/NZS
7000.
Tests
shall be performed after the substation earth mats at all ands of the line are
fully installed and connected.
6.5. OPGW
Tests
The
testing of system components to identify the apparent performance of the
optical fibres before and after the responsibility of the component has been
transferred between independent parties is essential.
EE
advocates that the stringing and splicing activities to be carried out by
specialised accredited service providers. It is mandatory that the following
testing procedures are implemented between each interface and progressively
throughout the works to ensure the separate activities are adequately
controlled.
The
AR is required to undertake the following tests –
- Drum Test - Upon OPGW receival from either the manufacturer or EE.
- Span Test - After OPGW stringing/installation.
- Splice Test - After OPGW splicing.
- Final Acceptance Test - After OPGW completion.
Each
test result shall be uniquely identified for future reference and shall include
a record of the environment at time of test and the person performing the test.
The attenuation data from the series of tests shall be compared to ensure that
there are no problems such as to allow the next step to commence. The
manufacturer’s factory test report for each drum of OPGW cable shall be made
available upon request.
The
consolidation and presentation to EE of all optical fibre measurements taken
during the course of works shall be in a final installation report within 10
working days of the final acceptance test.
6.6.1. OPGW Test Instruments
Either
“mini” or “Full Featured” Optical Time Domain Reflectometer (OTDR) instruments,
immune to polarisation noise and conforming to the Telcordia/Bellcore Standard
GR-196-CORE “Generic
Requirements
for Optical Time Domain Reflectometer – Type Equipment”, are to be used for all
OTDR measurements.
The
OTDR must be capable of storing the traces on an electronic medium (eg floppy
disk or USB stick) for transportation/submission, allow retrieval and reading
of traces. All traces are to be stored and submitted in a format compatible
OTDR 3.0 emulation software, the preferred trace formats are : Telcordia
standard SR4731 Rev 2.0 (SOR extension files) or GR 196 compatible file format.
The
OTDR testing is to be carried out at either 1310nm, 1550nm and/or 1625nm
wavelengths. The 1625nm OTDR trace is primarily used to identify pressure
points, macro bends and imperfections in cable installations.
The
OTDR operator must be experienced in the use of high performance OTDR’s and
shall, have attended an approved TITAB OTDR training course.
6.6.2. OPGW Cable & Splice Testing
Criteria
The
AR shall provide fusion splices with an average attenuation below 0.1dB when
measured at 1550nm. Any fusion splice with attenuation above 0.1dB shall be
re-spliced and re-tested.
The
approved methodology comprises measuring in both directions, using an OTDR, the
attenuation of each splice for all fibres. The average of the two readings for
each fibre will be accepted as the splice attenuation for each fibre. In
addition the end to end attenuation of each fibre in each direction shall be
measured using a calibrated light source and light meter.
All
measurements shall be made with an accuracy of 0.01dB and shall not be made
over sections greater than the capability of the OTDR in use.
Testing
of unterminated fibres shall be performed by splicing temporary pigtails to the
fibres or by using a Bare Fibre Adapter. A terminated fibre refers to fibres
terminated with connectors on patch panels at an ODF and/or at equipment.
6.6.3. Drum Test
Upon
receipt, by the AR, of the OPGW from either the AR’s supplier or EE the AR
shall check the cable attenuation and continuity of each drum. The AR shall
conduct a one way OTDR test for all optical fibres for all drums from the
inside end. The inside end of the cable is accessible for one way
OTDR
testing at the nominated wave lengths (1310, 1550 and/or1625nm), without
removing the laggings.
Following
testing the cable ends shall be resealed with a suitable heat shrink end cap to
ensure against moisture or dirt ingress.
The
AR shall give EE a minimum of 48hours notice before conducting these tests. If
the OPGW is supplied by EE the Drum Test is to be carried out at EE store prior
to transport to site.
Any
problems or discrepancies encountered shall be immediately reported to EE. The
AR shall provide EE with a report of test results within 10 working days of
product issue.
6.6.4 Span Test
The
span test is a two way OTDR test at the nominated wave lengths (1310, 1550
and/or 1625nm).
The
span test shall be conducted, by the AR, progressively as each drum is strung
and clamped off.
Any
problems are required to be identified and rectified prior to splicing.
The
same test equipment shall be used as for the Drum Test.
The
AR shall test the strung OPGW only after all clipping in is complete and in the
presence of an EE nominated representative at a time to be mutually agreed
upon. The AR shall notify EE at least 48hours in advance of the tests
proceeding.
6.6.5 Splice Test
The
AR shall measure the attenuation, of each splice, in both directions at both
1310nm and
1550nm.
The
AR shall submit to EE a Splice Testing Strategy. This strategy is to
demonstrate how the AR intends to measure each splice in order to guarantee the
average loss per splice was achieved throughout all the splices on the link.
The
same test equipment shall be used as for the previous tests undertaken.
6.6.6. Final Acceptance Test
The
AR shall measure the end to end attenuation of each optical fibre. The same
test equipment shall be used as for the previous tests undertaken.
The
AR shall submit to EE a Fibre Testing Strategy to guarantee the average loss
per splice was achieved throughout the fibre link.
The
AR shall present to EE the following data per fibre –
- Attenuation figures for each splice in both directions.
- An OTDR trace for each splice in both directions.
- End to end attenuation figures in both directions
- OTDR traces for each fibre in both directions.
7. POST COMMISSIONING TESTS
Are
placing the transmission line into service the following commissioning tests
may be required
- Radio Frequency Radiation Test.
- Thermal Scan under load.
These
tests may be requested by EE to be carried out by the ASP1 at full cost to the
ASP1. If required these tests will be requested prior to the end of the
construction warrenty period.
7.1. Radio Frequency Radiation Test
Radio
frequency radiation measurements are carried out to ensure that any
interference is less than the values specified in AS 2344 “Limits of
electromagnetic interference from overhead a.c. power lines and high voltage
equipment installations in the frequency range 0.15to 1000MHz”.
Where
interference exceeds these values, the sources of interference must be
identified and corrective action taken before re-testing.
Pls what is the standard for continuity and IRT test of transmission lines
ReplyDeleteTransmission Line Overview: Testing And Commissioning Procedure >>>>> Download Now
ReplyDelete>>>>> Download Full
Transmission Line Overview: Testing And Commissioning Procedure >>>>> Download LINK
>>>>> Download Now
Transmission Line Overview: Testing And Commissioning Procedure >>>>> Download Full
>>>>> Download LINK
Great and that i have a neat give: How To Budget House Renovation simple home renovations
ReplyDelete